WOAH! J&As

November 4, 2026 · sent Nov 4, 2026, 01:46 ET

WOAH! J&As — Nov 4: Army raises Missile Defense power-enclosure MATOC capacity to $948 million among 21 holders

1. Army raises Missile Defense power-enclosure MATOC capacity to $948 million among 21 holders

DEPT OF THE ARMY (DEPT OF DEFENSE) · Addon Services LLC · $498,000,000 (modification/increase) · 10 U.S.C. 3204(a)(1); RFO 6.103-1(c)(2)(ii)

Posted 2026-11-03, award FRR_VI_MATOC, “FRR MATOC Capacity Increase”

The Army Corps of Engineers Huntsville center seeks a $498,000,000 increase to the shared FRR VI MATOC ceiling, from $450,000,000 to $948,000,000, for the Missile Defense Agency's Modular Power Enclosures Program. The document says 64 task orders had been awarded as of 26 August 2026.

“This J&A requests an additional $498,000,000 in capacity to bring the new shared capacity to $948,000,000.”

— HNC FRR VI MATOC Capacity Increase Redacted.pdf, p. 1 (machine-transcribed page)

“Amount: The FRR VI MATOCs have a total shared capacity of $450,000,000.”

— HNC FRR VI MATOC Capacity Increase Redacted.pdf, p. 1 (machine-transcribed page) (source of the figure above, quoted by the checks)

2. Air Force sole-sources Shaw AFB power upgrade citing Operation EPIC FURY urgency

DEPT OF THE AIR FORCE (DEPT OF DEFENSE) · Stanley Drake Construction · value redacted · 10 U.S.C. 3204(a)(2); 10 U.S.C. § 3204(a)(1)

Posted 2026-11-03, “Repair Power B1921 - Justification for Other Than Full and Open Competition”

The Air Force cites unusual and compelling urgency tied to Operation EPIC FURY in the CENTCOM area for upgrading electrical power in Building 1921 at Shaw AFB. It says infrastructure degraded faster than anticipated and that a standard competition would take up to eight months.

“a standard competitive acquisition, which would require up to eight (8) months, would extend far beyond acceptable operational timelines and subject the mission to unacceptable risk.”

— B1921 Repair Power Unusual and Compelling Urgency_Red_Redacted.pdf, p. 3

3. DIA seeks to raise KBR threat-support IDIQ ceiling to $145 million, citing Golden Dome

DEFENSE INTELLIGENCE AGENCY (DIA) (DEPT OF DEFENSE) · KBR Wyle Services LLC. · $65,532,160 (modification/increase) · 10 U.S.C. § 3204(a)(1)

Posted 2026-11-03, award HHM402-21-D-0150, “DIA JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION”

DIA's Missile and Space Intelligence Center wants to lift the ceiling by $65,532,160 because requirements grew beyond original assumptions. The document points to added Golden Dome of America task orders and an expanded mission directed by SECWAR.

“TETRA's mission has been expanded by DOT&E, due to direction from SECWAR, to provide intelligence support to the entire of T&E community.”

— JOFOC HHM402-21-D-0150 CEILING INCREASE FINAL.pdf, p. 2 (machine-transcribed page)

“(U) The Missile and Space Intelligence Center (MSIC) is requesting approval to increase the ceiling for Indefinite Delivery/Indefinite Quantity (IDIQ) contract HHM402-21-D-0150 "Threat System Support" by $65,532,160.00 from $79,467,840.00 to $145,000,000.00.”

— JOFOC HHM402-21-D-0150 CEILING INCREASE FINAL.pdf, p. 1 (machine-transcribed page) (source of the figure above, quoted by the checks)

4. GSA extends MODES Bridge through April 2027 as GAO protest stays MODES III award

FEDERAL ACQUISITION SERVICE (GENERAL SERVICES ADMINISTRATION) · Miracle Systems LLC · value redacted · RFO-2025-16 FAR 16.507-6(b)(1)

Posted 2026-11-03, award 47QFCA24K0063, “MODES Bridge Extension”

A GAO protest of the MODES III award triggered an automatic CICA stay, so GSA proposes adding four option periods to the incumbent bridge. The document says the transition has been delayed up to 190 days.

“the timeline to transition performance from the MODES Bridge TO to the MODES III TO has been delayed up to 190 days”

— MODES_Bridge_Extension_-_JEFO (REDACTED)_Final.pdf, p. 2

All new notices (40)

Vendor, value and authority are shown only where the AI extraction found them with a quote checked against the document; blank means not extracted yet or not stated, not none. The one-line summaries are AI-written from each notice's text and are not quote-checked.

40 new notices reviewed (first collected Nov 3 01:16 ET to Nov 4 01:15 ET).